PirTano Construction completed installing the water main and fire hydrants along the project site.  Thank you for your patience during the water shut-down this week. The contractor also started work on the storm sewer at mid-block and going south.

Next week the contractor will continue to install storm sewer going south and begin pressure testing and disinfecting the new water main.

Water services are not scheduled to begin until after the July 4th Holiday. Notification will be given prior to shutting the water off to your residence.  

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.