Friday, July 20, 2012

PirTano Construction completed concrete pavement removal on the north half of the roadway this week. The contractor also performed tree removal for those trees that are in conflict with the proposed improvements.  

Next week the contractor will begin to install sanitary sewer main line and services on the north half of the road.  

Water services on the north half of the roadway are anticipated to begin the week of July 30th. Residents will be notified prior to this work beginning.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.