Friday, July 13, 2012

PirTano Construction completed storm sewer and sanitary sewer installation from mid-block to the south. The contractor also began installing water services on the south half of the block.

Next week the contractor will remove the existing concrete pavement on the north end of the roadway. The contractor will also begin underground utility installation on the north half of the block.

During the concrete pavement removal, getting through the street will be difficult. Pirtano will not start until 7:30 AM giving residents ample time to move their vehicles. All vehicles should be removed from Forest and parked on Laramie or Juniper during daytime working hours. There will be access at all times, but we appreciate your additional patience during this process.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.