Friday, July 6, 2012

PirTano Construction completed water main installation and pressure testing during this week. The contractor will begin disinfecting the new main this week and continue next week. The contractor also completed the storm sewer from mid-block to the south. The contractor started installing sanitary sewer mainline from mid-block to the south.

Limited work was performed on-site during this past week due to July 4th Holiday and excessive heat.

Next week the contractor will continue to install sanitary sewer mainline and services.

Water services will not begin until the new water main has passed all required testing. Notification will be given prior to shutting the water off to your residence.  

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.