Friday, August 10, 2012

PirTano Construction completed installing water services and sanitary sewer services along the north half of the roadway. All of the homes are now connected to the new water main and sanitary sewer. The contractor also connected the new water main to the existing water main and installed a new sanitary manhole on the south side of the roadway.

Next week the contractor anticipates to complete the storm sewer work on the north half of the roadway and begin roadway reconstruction of the entire roadway.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the construction operations and water service disruptions over the past several weeks.