PirTano Construction installed concrete curb & gutter on the east side of the roadway this week.  The contractor also performed driveway and sidewalk replacement on the east side of the roadway.

Next week the contractor will install concrete curb & gutter on the west side of the roadway.

Vehicles will need to be removed from driveways on the west side of the roadway starting Thursday, September 6 at 7:00 AM for final grading and setting of string line.  The concrete is anticipated to be installed on Friday. It is not anticipated that driveways on the west side of the roadway will be opened until Tuesday, September 11th.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the upcoming concrete installation and inconvenience of not being able to park in your driveways.