Friday, September 14, 2012

Last week, Alliance Contractors installed the concrete curb & gutter, driveways, and sidewalks on the west side of the roadway.

Those areas that did not have new concrete driveways installed, driveways access was restored on Thursday, September 13th.

Those residents with new concrete driveways installed will have access restored by Monday, September 17th.

PirTano Construction also began backfilling behind the curbs on the west side of the roadway.

Next week post-construction televising of the new sanitary and storm sewers will be performed. PirTano will also grade the road base in preparation for asphalt binder paving. Residents will not have access to their driveways from Tuesday until Wednesday. All work is weather dependant.

Asphalt binder paving is scheduled for next Wednesday, September 19th.

Prior to the asphalt surface being installed the contractor will need to perform structure adjustments in the roadway, landscape restoration with sod, and asphalt driveway restoration.  

Thank you for your patience during the past few weeks during concrete installation and inconvenience of not being able to park in your driveways.

Please be advised, parking restrictions along the street will remain in effect throughout the project, especially during grading and asphalt paving operations.