Friday, September 21, 2012



Last week, Pirtano Construction performed base grading and other work in preparation for asphalt paving. 

Peter Baker & Sons installed 2 layers of asphalt pavement last Wednesday.

Next week the contractor is scheduled to restore asphalt driveways and begin landscape restorations. The contractor is also scheduled to perform post-construction televising of the storm and sanitary sewers.

Following driveway and landscape restoration, the final surface of asphalt pavement will be installed.

Thank you for your patience throughout the construction project and the inconvenience the work  has caused.