Monday, October 1, 2012


Last week, the landscaping sub-contractor was on-site grading the parkways and placing topsoil in preparation for installing sod.

Peter Baker & Sons was on-site last week performing asphalt driveway restorations.

The post-construction televising of storm and sanitary sewers was also completed last week.

Next week, the landscaping sub-contractor is scheduled to continue grading and placing topsoil.  Sod installation is scheduled to begin on Monday, October 1st.

We are currently evaluating various options for improvements at the cul-de-sac on the south end of the roadway. Asphalt surface paving has been placed on hold until these options have been fully considered and a resolution determined.

Thank you for your patience throughout the construction season.