Friday, July 27, 2012

PirTano Construction completed sanitary sewer mainline improvements on the north half of the roadway.  

Next week the contractor will install sanitary sewer services and begin water service installation on the north half of the road. Residents will be notified prior to shutting the water off to your home.

During the water service installation the contractor will be required to transfer the individual water services for each home from the old main to the new main.  The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water.  The shutoff will last for 1 to 2 hours on average.  Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service.  If you have discolored water, please open your faucets and flush out the lines and water should clear up.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the construction operations and upcoming water service disruptions.

Friday, July 20, 2012

PirTano Construction completed concrete pavement removal on the north half of the roadway this week. The contractor also performed tree removal for those trees that are in conflict with the proposed improvements.  

Next week the contractor will begin to install sanitary sewer main line and services on the north half of the road.  

Water services on the north half of the roadway are anticipated to begin the week of July 30th. Residents will be notified prior to this work beginning.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Friday, July 13, 2012

PirTano Construction completed storm sewer and sanitary sewer installation from mid-block to the south. The contractor also began installing water services on the south half of the block.

Next week the contractor will remove the existing concrete pavement on the north end of the roadway. The contractor will also begin underground utility installation on the north half of the block.

During the concrete pavement removal, getting through the street will be difficult. Pirtano will not start until 7:30 AM giving residents ample time to move their vehicles. All vehicles should be removed from Forest and parked on Laramie or Juniper during daytime working hours. There will be access at all times, but we appreciate your additional patience during this process.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Friday, July 6, 2012

PirTano Construction completed water main installation and pressure testing during this week. The contractor will begin disinfecting the new main this week and continue next week. The contractor also completed the storm sewer from mid-block to the south. The contractor started installing sanitary sewer mainline from mid-block to the south.

Limited work was performed on-site during this past week due to July 4th Holiday and excessive heat.

Next week the contractor will continue to install sanitary sewer mainline and services.

Water services will not begin until the new water main has passed all required testing. Notification will be given prior to shutting the water off to your residence.  

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you in advance for your patience. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thursday, July 5, 2012

Pirtano Construction began construction of the sanitary sewer which is located in the center of Forest Road today.  Because this work is in the center of Forest Road we would like to advise residents to park their vehicles at the north end of Forest Road on the concrete pavement.  Thank you for your patience.