Friday, August 31, 2012

PirTano Construction installed concrete curb & gutter on the east side of the roadway this week.  The contractor also performed driveway and sidewalk replacement on the east side of the roadway.

Next week the contractor will install concrete curb & gutter on the west side of the roadway.

Vehicles will need to be removed from driveways on the west side of the roadway starting Thursday, September 6 at 7:00 AM for final grading and setting of string line.  The concrete is anticipated to be installed on Friday. It is not anticipated that driveways on the west side of the roadway will be opened until Tuesday, September 11th.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the upcoming concrete installation and inconvenience of not being able to park in your driveways.

Tuesday, August 28, 2012

Curb preparation and installation work on the east side of Forest Road started today but due to scheduling conflicts, the work is being pushed back one day.  Beginning Wednesday morning, August 29th final prep work will be completed and the curbs are scheduled to be poured Thursday and will be completed by Friday afternoon August 31st, depending on the weather.   Driveway access to these homes will be restored beginning Tuesday morning, September 4th. 

All cars parked at residences on the east side of Forest will not have access to driveways after 7:00 AM on Wednesday morning and should park on Juniper or Laramie, or talk to a neighbor on the west side to see if you can share driveways during both portions of the curb work. No cars should be parked on Forest Road between 7:00 AM and 6:00 PM.  Please plan accordingly. 

We apologize for any inconvenience this may have caused.

Saturday, August 25, 2012

PirTano Construction installed aggregate base course, removed and replaced poor sub-grade materials, and graded the roadway. The contractor also performed driveway and sidewalk removal on the east side of the roadway.

Next week the contractor will install concrete curb & gutter on the east side of the roadway.

Vehicles will need to be removed from driveway on the east side of the roadway starting Tuesday, August 28th at 7:00 AM for final grading and setting of string line.  The concrete is anticipated to be installed on Wednesday. It is not anticipated that driveways on the east of the roadway will be opened until Tuesday, September 4th.

Once the concrete work on the east side of the roadway is completed, the concrete work on the west side of the roadway will commence. This work is anticipated to started the week of September 4th.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the upcoming concrete installation and inconvenience of not being able to park in your driveways.

Saturday, August 18, 2012

PirTano Construction completed the remaining storm sewer, storm sewer services, and existing fire hydrant removals. The underground utility portion of the project is now completed. 

Next week Tuesday, the contractor will begin the roadway reconstruction process which includes removing the existing roadway material, repairing areas of failed sub-grade materials, installing new aggregate base, and grading the new aggregate.

Following the roadway reconstruction process, concrete curb & gutter will be installed.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the construction operations.

Friday, August 10, 2012

PirTano Construction completed installing water services and sanitary sewer services along the north half of the roadway. All of the homes are now connected to the new water main and sanitary sewer. The contractor also connected the new water main to the existing water main and installed a new sanitary manhole on the south side of the roadway.

Next week the contractor anticipates to complete the storm sewer work on the north half of the roadway and begin roadway reconstruction of the entire roadway.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the construction operations and water service disruptions over the past several weeks.

Friday, August 3, 2012

PirTano Construction installed sanitary sewer services and water services along the north of the roadway.

Next week the contractor will continue to install sanitary and water services, sanitary manholes, and begin storm sewer installation.

The contractor also anticipates performing a water main connection. The water main will be shut-down for 4-6 hours during this process. Residents will be notified 24-hours in advance of any water main shut-downs.

During the water service installation the contractor will be required to transfer the individual water services for each home from the old main to the new main.  The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water.  The shutoff will last for 1 to 2 hours on average.  Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service.  If you have discolored water, please open your faucets and flush out the lines and water should clear up.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the construction operations and upcoming water service disruptions.