Friday, September 21, 2012



Last week, Pirtano Construction performed base grading and other work in preparation for asphalt paving. 

Peter Baker & Sons installed 2 layers of asphalt pavement last Wednesday.

Next week the contractor is scheduled to restore asphalt driveways and begin landscape restorations. The contractor is also scheduled to perform post-construction televising of the storm and sanitary sewers.

Following driveway and landscape restoration, the final surface of asphalt pavement will be installed.

Thank you for your patience throughout the construction project and the inconvenience the work  has caused.

Friday, September 14, 2012

Last week, Alliance Contractors installed the concrete curb & gutter, driveways, and sidewalks on the west side of the roadway.

Those areas that did not have new concrete driveways installed, driveways access was restored on Thursday, September 13th.

Those residents with new concrete driveways installed will have access restored by Monday, September 17th.

PirTano Construction also began backfilling behind the curbs on the west side of the roadway.

Next week post-construction televising of the new sanitary and storm sewers will be performed. PirTano will also grade the road base in preparation for asphalt binder paving. Residents will not have access to their driveways from Tuesday until Wednesday. All work is weather dependant.

Asphalt binder paving is scheduled for next Wednesday, September 19th.

Prior to the asphalt surface being installed the contractor will need to perform structure adjustments in the roadway, landscape restoration with sod, and asphalt driveway restoration.  

Thank you for your patience during the past few weeks during concrete installation and inconvenience of not being able to park in your driveways.

Please be advised, parking restrictions along the street will remain in effect throughout the project, especially during grading and asphalt paving operations.

Friday, September 7, 2012

PirTano Construction installed aggregate base course and graded the roadway in preparation of concrete curb & gutter on the west side of the roadway. The contractor also removed several driveways along the west side of the roadway.

Unfortunately, due to the rain conditions on Friday, September 7th, the concrete curb and gutter on the west side of the roadway has been delayed.

The contractor will install the concrete curb & gutter on the west side of the roadway on Monday, September 10th.

Vehicles will need to be removed from driveways on the west side of the roadway starting Monday, September 10th at 7:00 AM for concrete curb & gutter and driveway installation. It is not anticipated that driveways on the west of the roadway will be opened until Friday, September 14th.

Once the concrete curb & gutter and driveway installation is completed, the contractor will begin grading behind the concrete curb & gutter.

Throughout the duration of the project, driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Please note the no parking on street signs posted for Monday through Friday 7 AM to 5 PM.

Thank you for your patience during the upcoming concrete installation and inconvenience of not being able to park in your driveways.